I am currently testing migration scenarios from On-Premises TFS 2012 to Visual Studio Online using the very recently released OpsHub tool. The process is working pretty smooth, however I am not sure if some of the behaviour I am experiencing is to be expected.

  • Our sprint start and end dates are not migrated, they show up empty in VSO. I am not sure if this is the result of an error on my part, or expected?

  • The burndown charts are not looking so cool anymore :), due to missing date fields in the tasks, I think this is a known limitation? But just wanted to verify this.

I have already read the documentation and realize that this might be what is described under limitations, but I just wanted to doublecheck since I am unsure.

1 Answers1

1

Yes. This is the expected behavior.

Sprint start and end dates are not migrated

The activity and change dates are set to migration date.

OpsHub
  • 36
  • 2
  • Is this still the case? Not having the correct dates is blocker for us adopting VSO. Is there another migration tool that can enable this? – cbailiss Dec 20 '15 at 19:06