I use TFS 2012 with the Microsoft Visual Studio Scrum 2.2 process template. I would like to see the iteration start and end date a Product Backlog item (PBI) is associated to on the PBI form itself?

If it's possible what fields do I need to refer to in the Work Item type definition?

If it's not possible, why not?

Bruno Bieri
  • 9,724
  • 11
  • 63
  • 92

1 Answers1

2

You could put the dates right in the Iteration names. So instead of "Iteration 1" you could call it "I1 - Oct 1-20"

Dylan Smith
  • 22,069
  • 2
  • 47