1

I am trying to find the date after specific number of days. My query looks like this:

UPDATE [PST].[dbo].[tbl_Project_tracker1]
SET    Predicted_Eng_Comp_date = tb2.Predicted_Eng_Comp_date
FROM   (SELECT NETWORK_NO, 
        dateadd(DAY, 20, Actual_Eng_Start_date) as Predicted_Eng_Comp_date
        FROM   [PST].[dbo].[tbl_Project_tracker1] 
       ) as tb2
WHERE  [NETWORK_NO] = tb2.[NETWORK_NO]

The query works fine but i am looking for working days. How do i calculate that?

GuidoG
  • 11,359
  • 6
  • 44
  • 79

1 Answers1

0

Please make use of below Query (Which replaces your current query):

    UPDATE [PST].[dbo].[tbl_Project_tracker1] SET Predicted_Eng_Comp_date = DATEADD(DAY, 20, Actual_Eng_Start_date)
Praveen ND
  • 540
  • 2
  • 10