I am trying to find the date after specific number of days. My query looks like this:
UPDATE [PST].[dbo].[tbl_Project_tracker1]
SET Predicted_Eng_Comp_date = tb2.Predicted_Eng_Comp_date
FROM (SELECT NETWORK_NO,
dateadd(DAY, 20, Actual_Eng_Start_date) as Predicted_Eng_Comp_date
FROM [PST].[dbo].[tbl_Project_tracker1]
) as tb2
WHERE [NETWORK_NO] = tb2.[NETWORK_NO]
The query works fine but i am looking for working days. How do i calculate that?