I have a query that I am surprised has not been asked before (or maybe my search skills are not that great)
We are following Scrum
and use Azure devops
to track it, in that the lowest grain is a task, that has Original Estimate
, Completed Work
and Remaining Work
If for some reason a task is started in a sprint and is not finished, there are Some Completed Hours and some Remaining Hours left on the task.
We want to create a query that shows us no. of hours worked on a task in current (given) sprint
so for example -
End of Sprint 1
Task 1 -
Original Estimate = 20 hrs
Completed hours = 12 hours
Remaining hours = 8 hours
Task 2 -
Original Estimate = 10 hrs
Completed hours = 5 hours
Remaining hours = 8 hours
End of Sprint 2
Task 1 -
Original Estimate = 20 hrs
Completed hours = 20 hours
Remaining hours = 0 hours
Status - done
Task 2 -
Original Estimate = 10 hrs
Completed hours = 13 hours
Remaining hours = 3 hours
Status - In progress
Now I want to see, how much effort was made in Sprint 2 for each task- Hence for
Task 1
8hrs - Planned
8hrs - completed
0 hrs - remaining
Task 2
8hrs - Planned
8hrs - completed
3 hrs - remaining
Hope it makes sense, please let me know if I could explain it any better.