I am using the Quartz Scheduling API for Java. Could you help me to run every 25 seconds using cron-expression. It's just a delay. It does not have to start always at second 0. For example, the sequence is like this: 0:00, 0:25, 0:50, 1:15, 1:40, 2:05, etc until minute 5 when the sequence begins again at second 0. Thank you.
7 Answers
I don't think cron expression will allow you to do that, but you can use
SimpleScheduleBuilder.repeatSecondlyForever( 25 )
as 300 (5 minutes) is a multiple of 25 it will repeat automatically.

- 1,266
- 2
- 13
- 30
If you want a job to trigger at a regular interval then you can use a Quartz SimpleTrigger
with a repeatInterval
specified.

- 1,721
- 1
- 19
- 29
-
6This is the correct answer to this question, chron expressions are not built for this particular task. – ug_ Jul 31 '13 at 20:43
With Quartz 2.1.5 this will help:
CronTrigger trigger = newTrigger()
.withIdentity("trigger1", "group1")
.withSchedule(cronSchedule("0/20 * * * * ?"))
.build();

- 1,456
- 18
- 25
-
4This is every 20 seconds, which works because 60 is a multiple of 20. OP explicitly asked for every 25 seconds, which this will not work for. – dcsohl Feb 26 '16 at 20:40
The only way to do this with a cron trigger is so complicated as to be useless; you're much better off with the SimpleTrigger from other answers. Nevertheless, if it has to be cron, you need to set up five different cron triggers:
0/25 0/5 * * * *
15/25 1/5 * * * *
5/25 2/5 * * * *
20/25 3/5 * * * *
10/25 4/5 * * * *
The first trigger fires at 0:00:25, 0:00:50; then the second trigger fires at 0:01:15 and 0:01:40; the third at 0:02:05, 0:02:30, 0:02:55; the fourth at 0:03:20, 0:03:45; and finally the fifth at 0:04:10 and 0:04:35. The first trigger then takes over again at 0:05:00, etc.
This only works because 25 seconds divides evenly into 5 minutes (which in turn goes evenly into an hour). If you wanted it every 23 seconds? Forget about it!

- 7,186
- 1
- 26
- 44
*/25 * * * * *
- [wiki] http://en.wikipedia.org/wiki/Cron
- [quartz tutorial] http://www.quartz-scheduler.org/docs/tutorial/TutorialLesson06.html

- 593
- 8
- 12
-
Logically this seems like like it should work, but it does not with the quartz version I have (2.0.1). It restarts from 0 seconds every minute just like 0/25. – rediVider May 22 '14 at 20:53
-
1This is not every 25 secs, but the sequence of the seconds goes like: 0 - 25 - 50 - 0 – Levent Divilioglu Jul 30 '19 at 10:46
You could schedule the job to run constantly but throttle the frequency using Camel's Throttler.
<route>
<from uri="jms:queue:TestQueue"/>
<!-- throttle 1 messages per 25 sec -->
<throttle timePeriodMillis="25000">
<constant>1</constant>
<to uri="bean:TestBean?method=testMethod"/>
</throttle>
</route>

- 389
- 1
- 13
You can't have a schedule like that for quartz.
One thing you could do is schedule a wrapper job to run every 5 seconds, and only do any work every fifth execution.

- 36,219
- 10
- 45
- 60