I am trying to find the total working days by specifying the first and end date and also the number of working days in a week. But unfortunately, the final result is coming wrong.
Below is my script
echo getWorkingDays("2022-04-01","2022-04-30",6)
function getWorkingDays($startDate,$endDate,$working_days_in_a_week){
// do strtotime calculations just once
$endDate = strtotime($endDate);
$startDate = strtotime($startDate);
//The total number of days between the two dates. We compute the no. of seconds and divide it to 60*60*24
//We add one to inlude both dates in the interval.
$days = ($endDate - $startDate) / 86400 + 1;
$no_full_weeks = floor($days / 7);
$no_remaining_days = fmod($days, 7);
//It will return 1 if it's Monday,.. ,7 for Sunday
$the_first_day_of_week = date("N", $startDate);
$the_last_day_of_week = date("N", $endDate);
//---->The two can be equal in leap years when february has 29 days, the equal sign is added here
//In the first case the whole interval is within a week, in the second case the interval falls in two weeks.
if ($the_first_day_of_week <= $the_last_day_of_week) {
if ($the_first_day_of_week <= 6 && 6 <= $the_last_day_of_week) $no_remaining_days--;
if ($the_first_day_of_week <= 7 && 7 <= $the_last_day_of_week) $no_remaining_days--;
}
else {
// (edit by Tokes to fix an edge case where the start day was a Sunday
// and the end day was NOT a Saturday)
// the day of the week for start is later than the day of the week for end
if($working_days_in_a_week !=7) {
if ($the_first_day_of_week == 7) {
// if the start date is a Sunday, then we definitely subtract 1 day
$no_remaining_days--;
if ($the_last_day_of_week == 6) {
// if the end date is a Saturday, then we subtract another day
$no_remaining_days--;
}
} else {
// the start date was a Saturday (or earlier), and the end date was (Mon..Fri)
// so we skip an entire weekend and subtract 2 days
$no_remaining_days -= 2;
}
}
}
//The no. of business days is: (number of weeks between the two dates) * (5 working days) + the remainder
//---->february in none leap years gave a remainder of 0 but still calculated weekends between first and last day, this is one way to fix it
$workingDays = $no_full_weeks * $working_days_in_a_week;
if ($no_remaining_days > 0 )
{
$workingDays += $no_remaining_days;
}
//We subtract the holidays
/*foreach($holidays as $holiday){
$time_stamp=strtotime($holiday);
//If the holiday doesn't fall in weekend
if ($startDate <= $time_stamp && $time_stamp <= $endDate && date("N",$time_stamp) != 6 && date("N",$time_stamp) != 7)
$workingDays--;
}*/
return $workingDays;
}
The final result is coming 25 when in fact the result should be 26 as there are only 4 Sundays in April and the number of business days in the week is 6 which means only Sunday is the weekend. What I am doing here? please help?