I am aware it is not good practice in terms of Scrum, but unfortunately we often have to change scope during our weekly Sprints.

During Sprint Review, how can I see what scope of work was added after the sprint was started? This can either be the sum of effort of User Stories added or by the remaining hours of their tasks added - ideally both.

The only resource I could find was this previous question about tracking individual items (unanswered), whereas what I care about is tracking the total effort/remaining hours added: How to track Azure work items that have been added into the sprint after the iteration start date?

Is this possible? Any information would be appreciated.

keipala
  • 768
  • 2
  • 7
  • 19

1 Answers1

0

When viewing the Analytics tab for the Sprint, the total scope increase is visible from the graph as well as the heading shown below. This suits our purposes.