Questions tagged [project-estimation]
2 questions
1
vote
2 answers
Formula for PERT - Pessimistic time and optimistic time
I found PERT examples include a formula
(a + 4m + b)/6
where a= optimistic time , b= pessimistic time and m= actual time to complete the task
but how to calculate a and b?
please help me as soon as possible

karthi
- 27
- 1
- 2
- 4
1
vote
2 answers
What to look for in estimating a PowerBuilder Conversion Project?
I've been trying to do a spec for a PowerBuilder 9 to 11.5
migration of a relatively complex application. Granted PowerBuilder
is not really my specialty I'm having issues trying to justify an
estimate for this part of the project (and theā¦

tekiegreg
- 1,667
- 6
- 25
- 41