Questions tagged [project-estimation]

2 questions
1
vote
2 answers

Formula for PERT - Pessimistic time and optimistic time

I found PERT examples include a formula (a + 4m + b)/6 where a= optimistic time , b= pessimistic time and m= actual time to complete the task but how to calculate a and b? please help me as soon as possible
karthi
  • 27
  • 1
  • 2
  • 4
1
vote
2 answers

What to look for in estimating a PowerBuilder Conversion Project?

I've been trying to do a spec for a PowerBuilder 9 to 11.5 migration of a relatively complex application. Granted PowerBuilder is not really my specialty I'm having issues trying to justify an estimate for this part of the project (and the…